Cost Overrun and Time Delay Risk Assessment in Local Road Bridge Construction using Fuzzy Inference System
Date
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
Pulchowk Campus
Abstract
Motorable Local Road Bridge Programm is a project implemented by Department of
Local Infrastructure initiated from February, 2011. Since its initiation, construction of
346 bridges have been completed through this program using unit rate NCB contract. The
current phase of this project has set target for completing construction of additional 200
bridges in coming four years.
The aim of this research is to assess and analyze the risk factors resulting in cost overrun
and time delay of completed bridges and use this knowledge for mitigation of risks in
future projects.
Risk factors were identified and classified through literature review. A fuzzy inference
system based model was developed using MATLAB for calculation of risk indices based
on questionnaire survey. A set of 57 bridges were sampled from the entire population for
validation of model.
The study identified Government regulations/contract awarded to lowest bidder,
inadequate budget allocation and unexpected ground condition as the highest ranked risk
factor causing cost overrun and time delay in local road bridge construction. Risk
management plan including risk response planning for mitigation was prepared for the
principal risk factors.
Risk indices obtained from the study can be used as weightage factors for developing a
neuro-fuzzy based prediction model.
Description
Motorable Local Road Bridge Programm is a project implemented by Department of
Local Infrastructure initiated from February, 2011.