Study on Transmission Pricing Mechanisms for Nepal Power Transmission Network
Date
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
Pulchowk Campus
Abstract
In this study on transmission pricing mechanism of Nepal Power Transmission
Network (NPTN), the postage stamp method was used for calculating the wheeling
charge (X1) for the consumers which were connected in loop network. The wheeling
charge (X1+X2) was paid by the consumers in radial network, where (X2) is the charge
calculated using the flow-based MW-mile method, using the Bialek’s algorithm.
The aforementioned algorithm was implemented on Bialek’s four bus and IEEE 14 bus
system. The annual revenue required for IEEE 14 bus system was estimated to be NPR
52.51 million. The total cost allocated to the generators and loads were NPR 59.04
million and NPR 85.83 million respectively which showed that the cost recovery is
possible using the power tracing method.
In case of NPTN, the wheeling charges (X1) calculated using postage stamp method
for the loop network was NPR 0.80/kWh. The wheeling charges (X2) for the Chameliya
HPP (CHPP) was NPR 8.72/ kWh. As the CHPP was using the loop network also, so
additional cost of NPR 0.80/kWh had been charged to CHPP and the total wheeling
charge (X1+X2) was calculated to be NPR 9.52 /kWh. The cost of the CHPP was the
highest among all the hydropower, this was because the CHPP had been using five
transmission lines to transfer its power to the national grid. In this study, the profit
margin was estimated to be 32% which was calculated assuming the payback period of
5 years. Based on the current calculated wheeling charge for the CHPP, the cash flow
for using the transmission line was generated and IRR for the same was obtained as
19% with cost and benefit ratio of using the alignment was found to be 20.23. The same
methodology was applied for calculating the wheeling charge for the radial network
Dhalkebar Muzzafarpur transmission line. The cost of the aforementioned transmission
line was calculated as NPR 1.06/kWh which was found to be 80.22% higher than the
original price of NPR 0.21 that was paid by the NEA to the PTCN in FY2018/19 for
the usage of the transmission line. The difference between the values could be due to
the different profit margin and payback period of the transmission company. The current study suggests that the transmission line wheeling charge will not only depend
on the usage of the network but also will depend on the profit margin and estimated
payback period which will be guided by the guidelines of the particular utility.
Description
In this study on transmission pricing mechanism of Nepal Power Transmission
Network (NPTN), the postage stamp method was used for calculating the wheeling
charge (X1) for the consumers which were connected in loop network.
Keywords
Citation
MASTER OF SCIENCE IN RENEWABLE ENERGY ENGINEERING